Edgbaston High School for Girls Thursday 29th July 2010

 

NEW BUILD UPDATE

Below is an update on the building work:

Undercroft

Under flooring soon to commence in this area, along with further mechanical installations.

Library

Awaiting structural works to be completed on the ground floor.

Atrium

Piling now complete to the front of the building. Final demolition is now taking place in this area. The ring beam which will form the foundations to the new structure is due to commence shortly.

Mr Smith
Project Manager

spellermetcalfe

 
To unsubscribe from this service please click here
Edgbaston High School for Girls, Westbourne Road, Edgbaston, Birmingham, B15 3TS, Tel: 0121 454 5831 Fax: 0121 454 2363